How the NPI Process Has Changed and Where We're Going

When forging into unknown territory or exploring new ground, it can help to look at where we’ve been so we can orient ourselves.

Just a few decades ago, electronics manufacturing companies were producing high volumes of few products. The efficiency of electronics manufacturing lines is measured by overall equipment effectiveness (OEE) and total effective equipment performance (TEEP). Back then, this meant optimizing the time it took to build a single board. If the time it took to build one board could be reduced by a few seconds, the savings would be multiplied by the number of boards being built. This could be in the hundreds of thousands or millions of boards, with no changes in the line configuration. If it took a day to change over from one product to another, it didn’t matter because the TEEP/OEE was driven by the time it took to build a board.

For example, consider that it takes 35 seconds to place components on a single board, and I need to make 250 boards. My handling time (the time it takes to load a board into the machine and get it out after) is 10 seconds, then the total time to build the 250 boards will be (35 + 10) • 250 = 11,250 seconds. This equates to about 188 minutes, or approximately three hours. If it takes four hours to changeover—namely reconfigure the line before starting a different PCB—to a new product, my OEE will be less than 50%, considering no other external factors. As the batch size goes down, the changeover time dominates the OEE figure.

In today’s high-mix, low-volume production environments, performance is further enhanced with line efficiency. Line efficiency is the ratio of the number of hours during which a high-volume, pick-and-place machine places parts on the PCB, divided by the number of hours during which the SMT assembly lines are staffed (placement time/staffed time x 100). It is a solid number, simple to obtain, and has great value as a key performance indicator.

With higher product mixes, the number of NPIs being processed increases. Changeovers on the shop-floor line can happen daily or many times a day. This also means the time it takes to process the source design data has increased. This data-processing time is becoming a more important consideration compared to when NPI processing was not a daily task in the lower mix environment. As product mix has gone up, there has been a move from mixed vendor lines focused on ultimate through-put to single vendor lines focused on flexibility and shorter changeovers. There may be more than one pick-and-place vendor brand in the factory, but each line commonly has only one brand now.

Download your free copy today! You can also view other titles in our full library.

We hope you enjoy The Electronics Industry’s Guide to… The Evolving PCB NPI Process.

Share




Suggested Items

Balancing Talent and Procurement Challenges

07/27/2022 | Nolan Johnson, I-Connect007
Ron Preston, vice president of supply chain at Green Circuits, outlines the company’s specific challenges with high-mix work. While the company excels at turning around boards in just a few days, difficulties in supply chain, materials, and staffing remain ever-present. What is to be done and how is Green Circuits working its way through these issues? The answers might surprise you.

VJ Electronix: Automating the X-ray Inspection Process

05/04/2022 | Nolan Johnson, I-Connect007
VJ Electronix's Brennan Caissie shares the benefits of a new inspection tool that can be used on a variety of boards, with an automated system that takes the pressure off the manufacturing floor operators and can provide feedback all the way to the design process.

This Month in SMT007 Magazine—Continuous Improvement: As Simple as X = Xc – 1

01/04/2021 | I-Connect007 Editorial Team
X=Xc – 1 is a conceptual equation for continuous improvement. You define X and work to reduce it by a factor of 1. This could be one work hour, one process step, one day less in a cycle, and so on. We recently met with Dr. Ron Lasky to discuss the concept of X=Xc – 1 and get his advice on generating enthusiasm among readers and the next generation about continuous improvement. As this discussion illustrates, many process improvements are small in scale, not yearlong, major efforts.



Copyright © 2023 I-Connect007 | IPC Publishing Group Inc. All rights reserved.